MINIM-MARTAP BAUXITE PROJECT: STEADY PROGRESS RECORDED ACROSS PROJECT SITES

The Minim-Martap bauxite project has reached a key milestone with the arrival, on schedule, of seven CRRC locomotives for the transport of ore to the Port of Douala.

The commissioning of the locomotives is underway. The wagon fleet is also taking shape, with 125 units already received and cleared through customs and a further 35 due in November 2026.

Meanwhile, construction is advancing along the mine-to-port corridor. The 43-kilometre road from the Danielle plateau to the Makor rail facility is built, with drainage and slope protection works still underway. At Makor, three railway tracks have been completed, while work continues on supporting facilities.

Preparations are also advancing at the mine, where the surface miner has been deployed and tested. Meanwhile, dredging, stockyard development and railway track rehabilitation are underway at the Port of Douala.

Together, these developments bring the CAMALCO project closer to operational readiness, with initial mining, transport and the first shipment planned for the first half of 2027.